Scope of Works:
- Chipping loose concrete if any.
- Sandblasting the exposed steel rebars to remove the rust.
- Apply protective coating, SikaTop Armatec 110 for all exposed steel rebars.
- Fixing steel shutter and opening on the steel shutter for fixing accessories.
- Sealing all around the shutter using Sikadur 31 CF Slow.
- Mixing and pumping Sikacrete 113PP using form & pump technique.
- Removing shutter and curing for 3 days.
- CLIENT QDVC-BIN OMRAN JV
- YEAR 2016
- WE DID CONCRETE REPAIR & GROUTING
- CATEGORY Concrete Repair & Grouting