Scope of Works:

  • Chipping loose concrete if any.
  • Sandblasting the exposed steel rebars to remove the rust.
  • Apply protective coating, SikaTop Armatec 110 for all exposed steel rebars.
  • Fixing steel shutter and opening on the steel shutter for fixing accessories.
  • Sealing all around the shutter using Sikadur 31 CF Slow.
  • Mixing and pumping Sikacrete 113PP using form & pump technique.
  • Removing shutter and curing for 3 days.